Mount Pleasant Village 3, BRAMPTON

Challenge: Weather & Schedule
During the Mount Pleasant project we experienced extreme weather conditions which threatened the delivery of the project.
The project was also a challenge due to a deep trunk sewer that was 10-12 meters in depth. It required complete granular backfill due to the local sewers being installed many meters above the main trunk collector. A lot of extra care had to be taken at these depths to prevent infiltration.
Despite the depth and extreme weather, we delivered the project on time.